Rex Booster Compressor Station
Client
Energy Transfer Partners
Powhatan, Ohio
- 30,000 cubic yards excavation for pipe trenches
- 2,500 cubic yards of concrete
- 3,700 linear feet of pipe trench inside plant
- Trenching for 5,000 linear feet of grounding and duct bank
Project Details
Scope of work for the construction of the booster compressor station included furnishing and installing concrete; excavation; backfill for compressor foundations, compressor building, and outside equipment; foundations for the ancillary buildings; V trenched, duct banks, site roads, and perimeter fencing. The facility has three compressors, process piping, and auxiliary equipment.