First Energy Bruce Mansfield
Client
First Energy Corp.
Shippingport, Pennsylvania
- 3,200-linear-foot conveyor system
- Equipment setting
- 16,000 yards concrete
- 1,280 tons structural steel
- 86,000 square feet 60 mil primary and secondary liner
- 41,000-square-foot building
Project Details
Mascaro was awarded a contract for the construction of a new dewatering plant with a pump house, utility bridges, barge loading facility, and miscellaneous platforms. The new facility processes 2.5 million to 3.5 million tons of byproduct each year consisting of fly ash, sulfur, and lime, a chemical used as part of a scrubbing process to address sulfur dioxide emissions. We provided the labor, equipment, and materials for the mechanical and electrical systems required to support the dewatering process. We also installed the soiling capping at their Little Blue Run waste facility.