Ellwood Water Treatment Plant / Raw Water Facilities
Client
Pennsylvania American Water Company
Wampum, Pennsylvania
- 12 acre site development
- 8 million gallon per day water treatment plant
- 14,000 cubic yards of concrete
- 55,000 SF of buildings
Project Details
The water treatment plant consists of a dewatering building, thickener tank, two clarifier tanks, water treatment building, switch gear building, and a hydrogen peroxide building. The main component of the raw water pump station is a 160-foot-deep, 27-foot-diameter shaft that will connect to raw water intake mains located in the Beaver River and Connoquenessing Creek.