AEP Mitchell
Client
American Electric Power Company
West Virginia
- Site preparation and underground utilities
- Foundations
- Trona mechanical installation
- Final grading and paving
- 2,000 lineal feet railroad track
- 10,000 cubic yards of concrete
Project Details
Mascaro was selected to oversee several projects at the Mitchell facility that included: limestone reclaim tunnel construction, gypsum storage building foundations and infrastructure, selective catalytic reduction (SCR) system installation, water treatment plant mechanical installation of piping, and installation of ZT Lines (2,800 linear feet of pipe, 5,640 linear feet of conduit).